Today met with electrician for electrical rough in.
Ask the electrician about the quotation of underground power, it is only for the main house, quoted at $1085 for 20 meter run of 16mm 3phase and plus 10mm tarif and 6 mm ground with 40mm heavy duty conduit. That is mean $51/meter run. Think this is too much, as far as I can remember at the electrical shop it cost around 32/m run for retail. I will check once again at the shop then query to the office and asked about credit for our allowance to the normal 10m power inlet.
How will I ask them to quote me for another 60meters to distribute to the shed?
I think I will do this after handover with other electrician.
When I was at the site with the electrican, the builder arrived with a guy, I think he bring one of his prospective client to see at the project, even he didn't said anything about the guest.
After brief through most power points, data points, switches etc with electrician, I went to the electrical shop, finding out that the prices of my preferred down lights has been increase by $2 each, not good, I need to buy 76 pcs of it.
At the afternoon I went back to the site with the kids, finding out that the tv antena has been installed, but at the north roof site, where all my solar panels will be mounted.
Again wrong location, location, location.
After wrong HSTP location, now tv antena. I rang the office and told about this, why they didn't ask me about the position, also I have already given them the layout of the solar panels position. Wrote email to rectify it and not to charge the cost to me.
I have to relocate the HSTP location (dig the and relocate the sewer pipes) on my cost, not for the tv antena again.
Hope they will understand.
Mei-Obet Home Freshwater Extended
Some posts are flash back, as we are new and beginner blogger. But we will try to catch up to date. Thanks for all senior blogger which allow us to make decision when we face the same situation. All comments and input are wellcome. Cheers
Monday, 30 May 2011
Sunday, 29 May 2011
28 May 2011 - day 73 New look
Went to the site early Saturday morning for mowing and see the house with the tile roof on. Looks like a house now.
These are the look:
These are the look:
front view
from backyard
Friday, 27 May 2011
27 May 2011 - day 72 Tile roof on
Visit the site in the morning and some workers were on the roof putting on the tile roof. The carperters also work today.
Some area has almost coverred such as alfresco area,
The builder ask about the name and contact number of engineer that gonna do the frame inspection. It is a bit weird for me, I told them I will be able to give the name after booked it because they have alot of engineer. Then they ask the name and contact number of the company. I gave them two companies name that probably will be used, depend on which one is availabe once they give me the schedule.
Received also the variation cost to install underground power 3phase for $1195. Not sure from what point to what point, whether including the distribution to the shed or not. The admin wrote to check with the electrician directly on Monday for electricity rough in.
Thursday, 26 May 2011
26 May 2011 - day 71 Preparation for Tile Roof Installation
Drop by at lunch time and see the roof with green colour as pictures below.
The workers were on the roof putting insulation material and preparing for tile roof instalation.
The workers were on the roof putting insulation material and preparing for tile roof instalation.
view from backyard
some areas hasn't have green cover
inside the house, ceiling look like this, some area hasn't been coverred
alfresco area covered completely
Wednesday, 25 May 2011
25 May 2011 - day 70 Fascia/Gutter installed
I went to the site around 5pm, the carpenter is still there. Very diligent.
The tile roof have been delivered, I think it was on Tuesday. There are 16 packs of tiles roof, magnum from Bristle. Some on the front of the house and some on the backyard. All fitting for the tiles also have been delivered.
The fascia and gutter also have been put on the trusses, off white colour.
The house is not looked as tall as before putting on fascia/gutter.
Because the shape of the roof is bending down on the eaves.
They are preparing the staggers to put on the roof tile this week. And the posts at the facade have been put also. Hope no more rain anymore until they put on the roof. I haven't seen any work done for strengthening the trusses. Hope they can do it before putting on the tile roof, otherwise will be quite difficult.
The house is not looked as tall as before putting on fascia/gutter.
Because the shape of the roof is bending down on the eaves.
They are preparing the staggers to put on the roof tile this week. And the posts at the facade have been put also. Hope no more rain anymore until they put on the roof. I haven't seen any work done for strengthening the trusses. Hope they can do it before putting on the tile roof, otherwise will be quite difficult.
front of the house
24 May 2011 - day 69 Email about Strengthening Trusses for Solar panel and Ducted air conditioning
Got the chance early in the morning to the site, find original bill letter from builder in the mail box.
Now I can see some speedbraces on the roof already:
No speedbrace at the backside yet, but probably they will finish putting all speedbrace today.
Sending email to the office that received the bill today and will process payment of frame stage by eft within 5 working days. Also ask the schedule for independent surveyor on frame stage. It is worthed to pay extra for the surveyor cause I think the frame stage is quite important, as all frames will be coverred with gyprocks and bricks, and we can't trace any technical issue after that. Totally different with slab stage, which we can see and judge the technical issue easily.
There is an email from office manager also with attachments about what required to be done on trusses to support 24 solar panels on the roof. She also mentioned that at the moment they don't know the dollar value for the work as there gonna be fair work to be done for that. I open the attachment, 5 pages explains that there are 7 trusses need to be strengthen by putting more support to the 4 webs on each trusses with another frame and batten screws.
Dollar value? When we started negotiation on the project, we have already told the builder that we will put on solar electricity and he said he will ask to strengthen the trusses for this purpose with no extra cost. I also write down on the carpenter plan to strengthen the roof for solar electricity installation. Also at many occasion we emphasize that we definitely will install solar electricity on the roof. Now they mentioned about dollar value.
I write back query and ask to include the work as frame part of the contract, the extra work on 7 trusses is a peanut work for his speedy carpenters.
The builder response directly and said that he manufactured the trusses on 31 March 2011, and we gave him the detail of frame composition on 14 April 2011. He mentioned also that writing to strengthen the roof on carpenter plan without detail is not enough. If we want them to strengthen the 18 trusses, it will go as variation otherwise we can do it later ourself after hand over.
Thinking that this is not the time for debating. When you face a problem like these, being humble and just throw some words that will hit the face, we do not have the right to judge, only He can do the judgement.
I wrote back mentioned that
we already emphasize in every occasion that we definitely install the panels and we gave the drawing on 16 April 2011 because we need feedback from the vendor. But how come he just coming back to us after more than 5 weeks (16 April 2011 - 23 May 2011).................................. I explain also that the work will be only on 7 trusses as what is written on the attachments from the engineer. I ended writing that we already include most works in the contract (flooring, aircon etc) and do want them to do this work as well and consider the cost of this variation for our tight budget.
Bring this to the prayer and let see later how much the cost will be.
Late afternoon the admin called inform about the detail of outdoor unit daikin ducted aircon, which had been asked a week ago. Apparently it is only 14.5KW capacity three phases. I had other quotation from independent vendor that we need at least 20KW capacity, so I told her that that capacity is too small for 3 meters ceiling with dark colour tile roof. I asked for a bigger capacity, and she said that company only provide this capacity, to upgrade for bigger one, we need a variation with extra $780 for 18KW. I think the extra cost is quite reasonable, so we settle this issue straight by signing the variation paper. I add one more vent to the ensuite with cost $360.- Happy with this result.
Hope their supplier can put the return air grill at the desired position around activity room or the coridor between bedrooms, not at the lounge as she mentioned at the first meeting.
Now I can see some speedbraces on the roof already:
left site of the house
No speedbrace at the backside yet, but probably they will finish putting all speedbrace today.
Sending email to the office that received the bill today and will process payment of frame stage by eft within 5 working days. Also ask the schedule for independent surveyor on frame stage. It is worthed to pay extra for the surveyor cause I think the frame stage is quite important, as all frames will be coverred with gyprocks and bricks, and we can't trace any technical issue after that. Totally different with slab stage, which we can see and judge the technical issue easily.
There is an email from office manager also with attachments about what required to be done on trusses to support 24 solar panels on the roof. She also mentioned that at the moment they don't know the dollar value for the work as there gonna be fair work to be done for that. I open the attachment, 5 pages explains that there are 7 trusses need to be strengthen by putting more support to the 4 webs on each trusses with another frame and batten screws.
Dollar value? When we started negotiation on the project, we have already told the builder that we will put on solar electricity and he said he will ask to strengthen the trusses for this purpose with no extra cost. I also write down on the carpenter plan to strengthen the roof for solar electricity installation. Also at many occasion we emphasize that we definitely will install solar electricity on the roof. Now they mentioned about dollar value.
I write back query and ask to include the work as frame part of the contract, the extra work on 7 trusses is a peanut work for his speedy carpenters.
The builder response directly and said that he manufactured the trusses on 31 March 2011, and we gave him the detail of frame composition on 14 April 2011. He mentioned also that writing to strengthen the roof on carpenter plan without detail is not enough. If we want them to strengthen the 18 trusses, it will go as variation otherwise we can do it later ourself after hand over.
Thinking that this is not the time for debating. When you face a problem like these, being humble and just throw some words that will hit the face, we do not have the right to judge, only He can do the judgement.
I wrote back mentioned that
we already emphasize in every occasion that we definitely install the panels and we gave the drawing on 16 April 2011 because we need feedback from the vendor. But how come he just coming back to us after more than 5 weeks (16 April 2011 - 23 May 2011).................................. I explain also that the work will be only on 7 trusses as what is written on the attachments from the engineer. I ended writing that we already include most works in the contract (flooring, aircon etc) and do want them to do this work as well and consider the cost of this variation for our tight budget.
Bring this to the prayer and let see later how much the cost will be.
Late afternoon the admin called inform about the detail of outdoor unit daikin ducted aircon, which had been asked a week ago. Apparently it is only 14.5KW capacity three phases. I had other quotation from independent vendor that we need at least 20KW capacity, so I told her that that capacity is too small for 3 meters ceiling with dark colour tile roof. I asked for a bigger capacity, and she said that company only provide this capacity, to upgrade for bigger one, we need a variation with extra $780 for 18KW. I think the extra cost is quite reasonable, so we settle this issue straight by signing the variation paper. I add one more vent to the ensuite with cost $360.- Happy with this result.
Hope their supplier can put the return air grill at the desired position around activity room or the coridor between bedrooms, not at the lounge as she mentioned at the first meeting.
22 may 2011 - day 67 Frame frame frame
It was raining in the morning, but the sun came out brightly after lunch time. Went to the site and took some pictures, all rooms look big with frame only. But later when the gyprock was put on the frame, probably will look different......... become smalller.
The house in frame from backyard, no speedbraces on the roof yet.
The next pictures are some main area in frame:
The house in frame from backyard, no speedbraces on the roof yet.
entry
garage
media room
kitchen look from alfresco
lounge