It was raining a few hours in the morning, stop.....then shower again from around 4 pm. Probably the carpenters kept working even in shower as the builder seem have a number of projects to catch up.
Got email from builder's office dated 19 May 2011, that practical completion of the building has been extended by 19 days and is now become 4 October 2011. These due to 8 wet days claims (from 16 days in March/April), 7 days delays by variation and 4 days delays by interruption of sand's delivery.
These letters seem like just admin procedure and protection to builder avoiding penaly of $50/day on overdue hand over on completion. Beliving that everything will be beautiful in His time.
kalo gak setuju yang 7 hari dan 4 hari gimana? artinya GJ ini sama aja tidak bertanggung jawab atas kontraktornya dong.
ReplyDeleteYang 8 hari itu gak ada alasan untuk tidak kerja karena waktu hujan aja kemaren mereka bikin concrete untuk tembok itu. Ini kan tergantung juga stage dan hari yang mana.. apa tuh hari 8 hari sepanjang hari hujan?