Friday, 27 May 2011

27 May 2011 - day 72 Tile roof on

Visit the site in the morning and some workers were on the roof putting on the tile roof. The carperters also work today.




Some area has almost coverred such as alfresco area,

The builder ask about the name and contact number of engineer that gonna do the frame inspection. It is a bit weird for me, I told them I will be able to give the name after booked it because they have alot of engineer. Then they ask the name and contact number of the company. I gave them two companies name that probably will be used, depend on which one is availabe once they give me the schedule.

Received also the variation cost to install underground power 3phase for $1195. Not sure from what point to what point, whether including the distribution to the shed or not. The admin wrote to check with the electrician directly on Monday  for electricity rough in.

No comments:

Post a Comment